[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110308,786,1,"单选题","下列公路隧道超欠挖控制的说法中，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应采取光面爆破、提高钻眼精度、控制药量等措施",false,{"key":16,"text":17,"correct":14},"B","当岩层完整、岩石抗压强度大于30MPa，允许岩石个别突出部分欠挖，但其隆起量不得大于50mm",{"key":19,"text":20,"correct":14},"C","宜采用断面仪或激光投影仪直接测定开挖面面积",{"key":22,"text":23,"correct":24},"D","当采用钢架支撑时，如围岩变形较大，支撑可能沉落或局部支撑难以拆除时，应适当减小开挖断面",true,"本题考核公路隧道超欠挖控制。当采用钢架支撑时，如围岩变形较大，支撑可能沉落或局部支撑难以拆除时，应适当加大开挖断面，预留支撑沉落量。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]