[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110307,786,1,"单选题","下列关于明洞施工说法，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","墙背回填应两侧对称进行",false,{"key":16,"text":17,"correct":14},"B","墙后有排水设施时，应与回填同时施工",{"key":19,"text":20,"correct":14},"C","靠山侧边墙顶或边墙墙后，应设置纵向和竖向盲管，将水引至边墙泄水孔排出",{"key":22,"text":23,"correct":24},"D","石质地层中墙背与岩壁空隙较大时，可采用与墙身同级混凝土回填；",true,"本题考查的是公路隧道洞口、明洞施工。石质地层中墙背与岩壁空隙不大时，可采用与墙身同级混凝土回填；空隙较大时，可采用片石混凝土或浆砌片石回填密实。土质地层，应将墙背坡面开凿成台阶状，用干砌片石分层码砌，缝隙用碎石填塞紧密，不得任意抛填土石。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]