[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110303,786,1,"单选题","洞内涌水或地下水位较高时，可采用（）和深井降水法处理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开挖截水沟",false,{"key":16,"text":17,"correct":14},"B","反坡排水",{"key":19,"text":20,"correct":21},"C","井点降水",true,{"key":23,"text":24,"correct":14},"D","平行导坑排水","本题考查的是公路隧道施工防排水。洞内涌水或地下水位较高时，可采用井点降水法和深井降水法处理。在隧道两侧地表面布置井点，间距宜为25～35m。井底应在隧底以下3～5m。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]