[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110302":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110302,786,1,"单选题","浅埋大跨度隧道及地表下沉量要求严格而围岩条件很差的情况时，应用（）方法进行隧道开挖。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","全断面法",false,{"key":16,"text":17,"correct":14},"B","台阶法",{"key":19,"text":20,"correct":14},"C","环形开挖留核心土法",{"key":22,"text":23,"correct":24},"D","双侧壁导坑法",true,"本题考核公路隧道主要开挖方式及适用范围。 全断面法—Ⅰ～Ⅲ级围岩、中小跨度隧道，Ⅳ级围岩中跨度隧道和Ⅲ级围岩大跨度隧道在采用了有效的预加固措施后，也可采用全断面法开挖。 台阶法--Ⅲ～Ⅴ级围岩的中小跨度隧道，Ⅵ级围岩的小跨度隧道在采用了有效的预加固措施后。 环形开挖预留核心土--Ⅴ～Ⅵ级围岩或一般土质围岩的中小跨度隧道，每循环开挖长度宜为0.5～1.0m，核心土面积不应小于整个断面的50%。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]