[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110301":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110301,786,1,"单选题","隧道初期支护施工中，施工现场喷射混凝土的工艺中使用较多的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","干喷法",false,{"key":16,"text":17,"correct":14},"B","潮喷法",{"key":19,"text":20,"correct":21},"C","湿喷法",true,{"key":23,"text":24,"correct":14},"D","混合喷射法","本题考点是公路隧道初期支护。喷射混凝土的工艺流程有干喷、潮喷和湿喷。干喷法因喷射速度大、粉尘污染及回弹情况较严重，隧道内喷射混凝土施工不得采用干喷工艺。潮喷法与干喷相比，上料、拌合及喷射时的粉尘少。湿喷法的粉尘和回弹量少，喷射混凝土的质量容易控制，但对喷射机械要求较高，机械清洗和故障处理较麻烦。目前施工现场湿喷法使用的较多。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]