[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110300,786,1,"单选题","隧道施工中，发现水体颜色或悬着物发生变化时，应采取（）处理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","正常施工",false,{"key":16,"text":17,"correct":18},"B","综合评价设计施工措施，加强监控量测，必要时采取相应工程对策",true,{"key":20,"text":21,"correct":14},"C","暂停施工，采取相应工程对策",{"key":23,"text":24,"correct":14},"D","认真进行安全技术交底，加快施工进度","本题考点是隧道施工监控量测技术。支护结构出现开裂、地表出现开裂、坍塌实行Ⅰ级管理--暂停施工，采取相应工程对策。渗水压力或水流量突然增大，水体颜色或悬着物发生变化，实行Ⅱ级管理--综合评价设计施工措施，加强监控量测，必要时采取相应工程对策。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]