[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110289,786,1,"单选题","后张法预制梁板的施工过程中，张拉应按设计要求在两端同时对称张拉，张拉时千斤顶的作用线必须与（）重合，两端各项张拉操作必须一致。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钢筋型心线",false,{"key":16,"text":17,"correct":18},"B","预应力轴线",true,{"key":20,"text":21,"correct":14},"C","梁截面轴线",{"key":23,"text":24,"correct":14},"D","弯矩影响线","本题考查的是桥梁上部结构装配式施工。按设计要求在两端同时对称张拉，张拉时千斤顶的作用线必须与预应力轴线重合，两端各项张拉操作必须一致。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]