[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110274,786,1,"单选题","为消除支架地基的不均匀沉降和支架的非弹性变形并获取弹性变形参数，应采用的手段是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预压",true,{"key":16,"text":17,"correct":18},"B","增加传力杆",false,{"key":20,"text":21,"correct":18},"C","硬化地面",{"key":23,"text":24,"correct":18},"D","增加剪刀撑","本题考查的是常用模板、支架和拱架的施工。应通过预压的方式，消除支架地基的不均匀沉降和支架的非弹性变形并获取弹性变形参数，或检验支架的安全性。预压荷载宜为支架需承受全部荷载的1.05～1.1倍。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]