[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110256,786,1,"单选题","关于先张法预应力钢筋张拉施工的说法，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","多根钢筋张拉时，其初应力要保持一致",false,{"key":16,"text":17,"correct":14},"B","热轧带肋钢筋张拉程序一般为：0→初应力→1.05σcon（持荷5min）→0.9σcon→σcon（锚固）",{"key":19,"text":20,"correct":14},"C","张拉时，张拉力方向与预应力钢材在一条直线上",{"key":22,"text":23,"correct":24},"D","同一构件内预应力钢筋断筋数量不得超过1%",true,"张拉时，同一构件内预应力钢丝、钢绞线的断丝数量不得超过1％，同时对于预应力钢筋不允许断筋。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]