[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110255,786,1,"单选题","下列预应力张拉要求中，错误的有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有几套张拉设备时，可根据现场情况随机组合使用",true,{"key":16,"text":17,"correct":18},"B","进行张拉作业前，必须对千斤顶进行标定",false,{"key":20,"text":21,"correct":18},"C","当梁体混凝土强度达到设计规定的张拉强度时，方可进行张拉",{"key":23,"text":24,"correct":18},"D","预应力筋锚固后的外露长度不宜小于30mm，且不应小于1.5倍预应力筋直径。","在进行张拉作业前，必须对千斤顶、油泵进行配套标定，并每隔一段时间进行一次校验。有几套张拉设备时，要进行编组，不同组号的设备不得混用。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]