[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110254,786,1,"单选题","桥梁桩基础正循环回转钻孔施工中，护壁泥浆循环路径包括：①桩；②钻杆中心；③钻头口；④泥浆泵笼头；⑤泥浆沉淀池。则泥浆循环的正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④→⑤",false,{"key":16,"text":17,"correct":18},"B","④→②→③→①→⑤",true,{"key":20,"text":21,"correct":14},"C","②→③→④→①→⑤",{"key":23,"text":24,"correct":14},"D","⑤→①→③→②→④","正循环回转钻孔：钻具旋转切削土体钻进，泥浆泵将泥浆压进泥浆笼头，通过钻杆中心从钻头喷入钻孔内，泥浆挟带钻渣沿钻孔上升，从护筒顶部排浆孔排出至沉淀池，钻渣在此沉淀而泥浆流入泥浆池循环使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]