[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110231,786,1,"单选题","关于水泥稳定土路拌法碾压施工的做法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拌合均匀后，应用钢轮压路机快速碾压一遍",false,{"key":16,"text":17,"correct":18},"B","同日施工的两工作段的衔接处，前一段拌合整形后留5～8m与后一段再加水泥重新拌合后一起碾压",true,{"key":20,"text":21,"correct":14},"C","当必须分两幅施工时，纵缝必须斜接，不得垂直相接",{"key":23,"text":24,"correct":14},"D","应先采用重型压路机后采用轻型压路机进行碾压","本题考查的是基层（底基层）混合料生产、摊铺及碾压。无机结合料基层路拌法碾压施工：拌合均匀后，及时用平地机初步整形再用拖拉机、平地机或轮胎压路机快速碾压一遍。水泥稳定材料层的施工应避免纵向接缝。分两幅施工时，纵缝应垂直相接。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]