[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110206,786,1,"单选题","在路拌法水泥稳定土基层施工中，主要工艺流程有：①准备下承层；②洒水闷料；③拌合；④整形；⑤碾压；⑥养生。如下选项中排序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤⑥",true,{"key":16,"text":17,"correct":18},"B","②①③④⑤⑥",false,{"key":20,"text":21,"correct":18},"C","①②④③⑤⑥",{"key":23,"text":24,"correct":18},"D","①③②④⑤⑥","本题考核的是混合料生产、摊铺及碾压。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]