[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110198,786,1,"单选题","下面关于土石路堤施工技术说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","性质不同的填料，应水平分层、分段填筑，分层压实",false,{"key":16,"text":17,"correct":14},"B","土石路堤不得倾填",{"key":19,"text":20,"correct":14},"C","施工前应由试验确定松铺厚度、机械、压实速度及遍数、沉降差等参数",{"key":22,"text":23,"correct":24},"D","透水性差异大的材料，分层或分段填筑，宜纵向分幅填筑",true,"本题考查的是土石路堤施工技术。透水性差异大的材料，分层或分段填筑，不宜纵向分幅填筑。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]