[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110193,786,1,"单选题","下列不是路基横向开裂的原因是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","使用了不合格的土做填料",false,{"key":16,"text":17,"correct":18},"B","半填半挖路段未按要求设台阶",true,{"key":20,"text":21,"correct":14},"C","同一天填筑层路基填料混杂",{"key":23,"text":24,"correct":14},"D","压实度不符合要求","本题考查的是路基横向裂缝病害及防治措施。原因分析：（1）路基填料直接使用了液限大于50%、塑性指数大于26的土；（2）同一填筑层路基填料混杂，塑性指数相差悬殊；（3）路基顶填筑层作业段衔接施工工艺不符合规范要求；（4）路基顶下层平整度填筑层厚度相差悬殊，且最小压实厚度小于8cm；（5）暗涵结构物基底沉降或涵背回填压实度不符合规定。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]