[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110191,786,1,"单选题","关于场地清理的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","取土坑范围内的树根应全部挖除",false,{"key":16,"text":17,"correct":14},"B","填方高度大于1m的高速公路路堤，基底树根应全部挖除",{"key":19,"text":20,"correct":21},"C","清出的表层土不能作路基使用",true,{"key":23,"text":24,"correct":14},"D","填方高度大于1m的二级以下公路路堤，可保留树根","本题考查的是路基施工准备。二级及二级以上公路路堤和填方高度小于1m的公路路堤，应将路基基底范围内的树根全部挖除，并将坑穴填平夯实；填方高度大于1m的二级以下公路路堤，可保留树根，但根部不能露出地面。取土坑范围内的树根应全部挖除。清出的表层土宜充分利用。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]