[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110177,786,1,"单选题","在用袋装砂井法进行软土处理施工工艺程序中，正确的程序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","整平原地面→机具定位→摊铺下层砂垫层→打入套管→沉入砂袋→拔出套管→机具移位→埋砂袋头→摊铺上层砂垫层",false,{"key":16,"text":17,"correct":14},"B","整平原地面→摊铺下层砂垫层→机具定位→沉入砂袋→打入套管→拔出套管→机具移位→埋砂袋头→摊铺上层砂垫层",{"key":19,"text":20,"correct":21},"C","整平原地面→摊铺下层砂垫层→机具定位→打入套管→沉入砂袋→拔出套管→机具移位→埋砂袋头→摊铺上层砂垫层",true,{"key":23,"text":24,"correct":14},"D","整平原地面→摊铺下层砂垫层→机具定位→打入套管→沉入砂袋→拔出套管→机具移位→摊铺上层砂垫层→埋砂袋头","用插板机，或与袋装砂井打设机共用（将圆形套管换成矩形套管）。按整平原地面→摊铺下层砂垫层→机具就位→塑料排水板穿靴→插入套管→拔出套管→割断塑料排水板→机具移位→摊铺上层砂垫层的施工工艺程序进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]