[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110176,786,1,"单选题","软土地基处理中抛石挤淤施工规定说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开",false,{"key":16,"text":17,"correct":18},"B","当下卧地层具有明显横向坡度时，应从下卧层低的一侧向高的一侧扩展，并在低侧边部多抛投不少于2m宽",true,{"key":20,"text":21,"correct":14},"C","在抛石高出水面后，应采用重型机具碾压紧密，然后在其上设反滤层，再填土压实",{"key":23,"text":24,"correct":14},"D","抛石挤淤法一般适用于处理深度不宜大于3m","抛石挤淤施工规定： （1）当下卧地层平坦时，应沿道路中线向前呈三角形抛填，再渐次向两旁展开，将淤泥挤向两侧。当下卧地层具有明显横向坡度时，应从下卧层高的一侧向低的一侧扩展，并在低侧边部多抛投不少于2m宽，形成平台顶面。 （3）在抛石高出水面后，应采用重型机具碾压紧密，然后在其上设反滤层，再填土压实。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]