[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110170,786,1,"单选题","塑料排水板的施工工艺流程中，“插入套管”的前一道工序是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拔出套管",false,{"key":16,"text":17,"correct":14},"B","隔断塑料排水板",{"key":19,"text":20,"correct":14},"C","机具就位",{"key":22,"text":23,"correct":24},"D","塑料排水板穿靴",true,"本题考查的是软土路基处理施工技术。塑料排水板；按整平原地面→摊铺下层砂垫层→机具就位→塑料排水板穿靴→插入套管→隔断塑料排水板→机具移位→摊铺上层砂垫层的施工工艺程序进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建公路工程实务","建筑工程",0]