[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-783-9":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":607},{"id":5,"name":6,"category":7,"favorite":8},783,"目标控制（土木建筑）","建筑工程",0,9,50,2641,[13,34,46,58,70,82,94,105,117,129,141,153,165,174,186,198,209,221,233,245,257,269,281,293,305,317,329,341,353,365,373,385,397,409,421,433,445,453,465,477,489,501,513,524,536,548,559,571,583,595],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":27,"analysis":33},1107605,1,"单选题","按子项目将投资目标分解后，编制工程分项的投资支出计划。下列属于详细的资金使用计划表应有内容的是（ ）。",[19,23,26,30],{"key":20,"text":21,"correct":22},"A","工程单位编码",false,{"key":24,"text":25,"correct":22},"B","实际综合单价",{"key":27,"text":28,"correct":29},"C","计量单位",true,{"key":31,"text":32,"correct":22},"D","质量要求","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},1107606,"某工程基础底板的设计厚度为1.5米，施工单位实际施工的厚度为1.6米，在工程款的计量、支付时，多做部分的工程量应（ ）。",[38,40,42,44],{"key":20,"text":39,"correct":29},"不予计量",{"key":24,"text":41,"correct":22},"予以计量",{"key":27,"text":43,"correct":22},"计量一半",{"key":31,"text":45,"correct":22},"由业主与施工单位协商处理",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":20,"analysis":33},1107607,"根据《建设工程施工合同（示范成本）》GF－2017－0201，监理人应在收到承包人提交的工程量报告后（ ）天内，完成对工程量报表的审核并发送发包人。",[50,52,54,56],{"key":20,"text":51,"correct":29},"7",{"key":24,"text":53,"correct":22},"14",{"key":27,"text":55,"correct":22},"21",{"key":31,"text":57,"correct":22},"28",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":24,"analysis":33},1107608,"建筑工程险保险费项目一般按（ ）进行计量支付。",[62,64,66,68],{"key":20,"text":63,"correct":22},"均摊法",{"key":24,"text":65,"correct":29},"凭据法",{"key":27,"text":67,"correct":22},"估价法",{"key":31,"text":69,"correct":22},"分解计量法",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},1107609,"工程量计算规范是确定（ ）的依据。",[74,76,78,80],{"key":20,"text":75,"correct":22},"计价规则",{"key":24,"text":77,"correct":29},"计量方法",{"key":27,"text":79,"correct":22},"合同结算",{"key":31,"text":81,"correct":22},"竣工决算",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":20,"analysis":33},1107610,"（ ）是计量监理的基础。",[86,88,90,92],{"key":20,"text":87,"correct":29},"质量监理",{"key":24,"text":89,"correct":22},"投资监理",{"key":27,"text":91,"correct":22},"投资控制",{"key":31,"text":93,"correct":22},"进度控制",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":20,"analysis":33},1107611,"对于不符合合同文件要求的工程，承包人超出施工图纸范围或因承包人原因造成返工的工程量，应（ ）。",[98,99,101,103],{"key":20,"text":39,"correct":29},{"key":24,"text":100,"correct":22},"酌情计量",{"key":27,"text":102,"correct":22},"全部计量",{"key":31,"text":104,"correct":22},"减半计量",{"id":106,"libraryId":5,"type":15,"typeLabel":16,"stem":107,"options":108,"answer":20,"analysis":33},1107612,"根据《建设工程工程量清单计价规范》，当承包人投标报价中材料单价低于基准单价时，施工期间材料单价跌幅以（ ）为基础，超过合同约定的风险幅度值的，其超过部分按实调整。",[109,111,113,115],{"key":20,"text":110,"correct":29},"投标报价",{"key":24,"text":112,"correct":22},"招标控制价",{"key":27,"text":114,"correct":22},"基准单价",{"key":31,"text":116,"correct":22},"实际单价",{"id":118,"libraryId":5,"type":15,"typeLabel":16,"stem":119,"options":120,"answer":20,"analysis":33},1107613,"2018年3月，实际完成的某工程基准日期的价格为1500万元。调值公式中的固定系数为0.3，对比基准日前的相关成本要素，水泥的价格指数上升了20%，水泥的费用占合同调值部分的40%，其它成本要素的价格均未发生变化。则2018年3月，应调整的合同价的差额为（ ）万元。",[121,123,125,127],{"key":20,"text":122,"correct":29},"84",{"key":24,"text":124,"correct":22},"126",{"key":27,"text":126,"correct":22},"1584",{"key":31,"text":128,"correct":22},"1626",{"id":130,"libraryId":5,"type":15,"typeLabel":16,"stem":131,"options":132,"answer":20,"analysis":33},1107614,"某工程施工合同约定采用造价信息进行价格调整。施工期间，项目所在地省级造价管理机构发布了工人工资指导价上调10%的通知并即时生效，该工程在颁布通知当月完成的合同价款为300万元，其中人工费为60万元（已知该人工费单价比发布的指导价高出30%），则该工程当月人工费结算的做法是（ ）。",[133,135,137,139],{"key":20,"text":134,"correct":29},"不予上调",{"key":24,"text":136,"correct":22},"按照通知要求上调10%",{"key":27,"text":138,"correct":22},"由总监理工程师确定新的单价",{"key":31,"text":140,"correct":22},"由发承包双方协商后适当调整",{"id":142,"libraryId":5,"type":15,"typeLabel":16,"stem":143,"options":144,"answer":24,"analysis":33},1107615,"某工程项目的招标控制价为400元，投标报价为320元，投标报价浮动率为5%。如果履行合同过程中，其工程量的偏差达到20%，则其综合单价应调整为（ ）元。",[145,147,149,151],{"key":20,"text":146,"correct":22},"320",{"key":24,"text":148,"correct":29},"323",{"key":27,"text":150,"correct":22},"400",{"key":31,"text":152,"correct":22},"460",{"id":154,"libraryId":5,"type":15,"typeLabel":16,"stem":155,"options":156,"answer":27,"analysis":33},1107616,"某混凝土工程招标工程量为900m3，综合单价为350元\u002Fm3。在施工过程中由于设计变更导致实际完成工程量为1150m3。合同约定：当实际完成工程量增加超过15%时，超出部分的综合单价要调低，调价系数为0.9。该混凝土工程实际结算工程款为（ ）万元。",[157,159,161,163],{"key":20,"text":158,"correct":22},"36.2250",{"key":24,"text":160,"correct":22},"39.3750",{"key":27,"text":162,"correct":29},"39.8475",{"key":31,"text":164,"correct":22},"40.2500",{"id":166,"libraryId":5,"type":15,"typeLabel":16,"stem":167,"options":168,"answer":24,"analysis":33},1107617,"在合同价款调整中，出现合同价款调增事项后的（ ）天内，承包人应向发包人提交合同价款调增报告并附上相关资料。",[169,170,171,172],{"key":20,"text":51,"correct":22},{"key":24,"text":53,"correct":29},{"key":27,"text":57,"correct":22},{"key":31,"text":173,"correct":22},"30",{"id":175,"libraryId":5,"type":15,"typeLabel":16,"stem":176,"options":177,"answer":24,"analysis":33},1107618,"任一计日工项目持续进行时，承包人应在该项工作（ ）的24h内向发包人提交有计日工记录汇总的现场签证报告一式三份。",[178,180,182,184],{"key":20,"text":179,"correct":22},"实施开始时间",{"key":24,"text":181,"correct":29},"实施结束时间",{"key":27,"text":183,"correct":22},"发包人通知承包人时间",{"key":31,"text":185,"correct":22},"发包人确认时间",{"id":187,"libraryId":5,"type":15,"typeLabel":16,"stem":188,"options":189,"answer":24,"analysis":33},1107619,"承包人采购材料和工程设备的，应在合同中约定主要材料、工程设备价格变化的范围或幅度；当没有约定，且材料、工程设备单价变化超过（ ）时，超过部分的价格应按照价格指数调整法或造价信息差额调整法计算调整材料、工程设备费。",[190,192,194,196],{"key":20,"text":191,"correct":22},"10%",{"key":24,"text":193,"correct":29},"5%",{"key":27,"text":195,"correct":22},"4%",{"key":31,"text":197,"correct":22},"3%",{"id":199,"libraryId":5,"type":15,"typeLabel":16,"stem":200,"options":201,"answer":24,"analysis":33},1107620,"根据《建设工程工程量清单计价规范》GB50500－2013条款，如果工程量偏差和工程变更等原因导致工程量偏差超过（ ）时，可进行合同价款调整。",[202,203,205,207],{"key":20,"text":191,"correct":22},{"key":24,"text":204,"correct":29},"15%",{"key":27,"text":206,"correct":22},"20%",{"key":31,"text":208,"correct":22},"25%",{"id":210,"libraryId":5,"type":15,"typeLabel":16,"stem":211,"options":212,"answer":31,"analysis":33},1107621,"某招标项目，承包人报价值为3000万元，经修正后的，发承包双方以均认可的2900万元签约合同。该项目招标控制价位3100万元，承包人施工图预算为3050万元。则承包人报价浮动率是（ ）。",[213,215,217,219],{"key":20,"text":214,"correct":22},"1.64%",{"key":24,"text":216,"correct":22},"3.22%",{"key":27,"text":218,"correct":22},"3.33%",{"key":31,"text":220,"correct":29},"6.45%",{"id":222,"libraryId":5,"type":15,"typeLabel":16,"stem":223,"options":224,"answer":27,"analysis":33},1107622,"某工程的招标控制价为800万元，中标人的投标报价为777万元，施工图预算造价为780万元，则承包人的报价浮动率为（ ）。",[225,227,229,231],{"key":20,"text":226,"correct":22},"0.04%",{"key":24,"text":228,"correct":22},"2.50%",{"key":27,"text":230,"correct":29},"2.88%",{"key":31,"text":232,"correct":22},"2.96%",{"id":234,"libraryId":5,"type":15,"typeLabel":16,"stem":235,"options":236,"answer":27,"analysis":33},1107624,"下列承包人索赔中，可以获得费用及利润的是（ ）索赔。",[237,239,241,243],{"key":20,"text":238,"correct":22},"加速施工费用",{"key":24,"text":240,"correct":22},"拖延支付工程款",{"key":27,"text":242,"correct":29},"发包人不正当地终止工程引起",{"key":31,"text":244,"correct":22},"汇率变化引起",{"id":246,"libraryId":5,"type":15,"typeLabel":16,"stem":247,"options":248,"answer":24,"analysis":33},1107625,"根据计价规范规定，发包人应在收到承包人的现场签证报告后的（ ）内进行核实，给予确认或提出修改意见。",[249,251,253,255],{"key":20,"text":250,"correct":22},"24小时",{"key":24,"text":252,"correct":29},"48小时",{"key":27,"text":254,"correct":22},"7天",{"key":31,"text":256,"correct":22},"14天",{"id":258,"libraryId":5,"type":15,"typeLabel":16,"stem":259,"options":260,"answer":24,"analysis":33},1107626,"下列属于承包人对发包人索赔内容的是（ ）。",[261,263,265,267],{"key":20,"text":262,"correct":22},"工期延误索赔",{"key":24,"text":264,"correct":29},"不利的自然条件与人为障碍",{"key":27,"text":266,"correct":22},"对超额利润的索赔",{"key":31,"text":268,"correct":22},"对承包人不正当的放弃工程",{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":31,"analysis":33},1107627,"下列工期事件的索赔中，承包人可以得到利润补偿的是（ ）。",[273,275,277,279],{"key":20,"text":274,"correct":22},"异常不利的气候条件",{"key":24,"text":276,"correct":22},"施工中遇到不利物质条件",{"key":27,"text":278,"correct":22},"施工中遇到化石、文物",{"key":31,"text":280,"correct":29},"发包人提供的设计图纸错误",{"id":282,"libraryId":5,"type":15,"typeLabel":16,"stem":283,"options":284,"answer":31,"analysis":33},1107628,"对于因异常恶劣的气候造成施工单位的施工机械损坏和人员窝工以及相应的费用索赔，监理工程师应当（ ）。",[285,287,289,291],{"key":20,"text":286,"correct":22},"批准相应的施工机械损坏和人员窝工费用",{"key":24,"text":288,"correct":22},"批准相应的人工、材料、机具费",{"key":27,"text":290,"correct":22},"批准相应的措施项目费",{"key":31,"text":292,"correct":29},"不予批准",{"id":294,"libraryId":5,"type":15,"typeLabel":16,"stem":295,"options":296,"answer":27,"analysis":33},1107629,"现场签证有多种情形，下列属于需要现场签证的是（ ）。",[297,299,301,303],{"key":20,"text":298,"correct":22},"合同中约定材料的市场价格未发生变化",{"key":24,"text":300,"correct":22},"合同工程招标工程量清单中没有",{"key":27,"text":302,"correct":29},"发包人的口头指令",{"key":31,"text":304,"correct":22},"由于承包人原因造成施工现场停电",{"id":306,"libraryId":5,"type":15,"typeLabel":16,"stem":307,"options":308,"answer":24,"analysis":33},1107630,"下列事件中，需要进行现场签证的是（ ）。",[309,311,313,315],{"key":20,"text":310,"correct":22},"合同范围以内零星工程的确认",{"key":24,"text":312,"correct":29},"修改施工方案引起工程量增减的确认",{"key":27,"text":314,"correct":22},"承包人原因导致设备窝工损失的确认",{"key":31,"text":316,"correct":22},"合同范围以外新增工程的确认",{"id":318,"libraryId":5,"type":15,"typeLabel":16,"stem":319,"options":320,"answer":20,"analysis":33},1107631,"在《标准施工招标文件》合同条款中，承包商只可以获得费用补偿的是（ ）。",[321,323,325,327],{"key":20,"text":322,"correct":29},"发包人要求承包人提前竣工",{"key":24,"text":324,"correct":22},"发包人原因引起的暂停施工",{"key":27,"text":326,"correct":22},"发包人原因造成工期延误",{"key":31,"text":328,"correct":22},"发包人原因导致试运行失败",{"id":330,"libraryId":5,"type":15,"typeLabel":16,"stem":331,"options":332,"answer":20,"analysis":33},1107632,"根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，下列选项中属于发包人向承包人索赔的是（ ）。",[333,335,337,339],{"key":20,"text":334,"correct":29},"质量不满足合同要求索赔",{"key":24,"text":336,"correct":22},"不利的自然条件引起的索赔",{"key":27,"text":338,"correct":22},"认为障碍引起的索赔",{"key":31,"text":340,"correct":22},"不可抗力",{"id":342,"libraryId":5,"type":15,"typeLabel":16,"stem":343,"options":344,"answer":31,"analysis":33},1107633,"根据FIDIC《施工合同条件》有关索赔条款，当业主要求工程变更时，承包商可以要求的索赔内容是（ ）。",[345,347,349,351],{"key":20,"text":346,"correct":22},"仅工期＋费用索赔",{"key":24,"text":348,"correct":22},"仅工期索赔",{"key":27,"text":350,"correct":22},"仅费用＋利润索赔",{"key":31,"text":352,"correct":29},"工期＋费用＋利润索赔",{"id":354,"libraryId":5,"type":15,"typeLabel":16,"stem":355,"options":356,"answer":31,"analysis":33},1107634,"某工程承包合同总额为9000万元，主要材料及构件所占比重为60%，工程预付款为合同总额的20%，则工程预付款的起扣点为（ ）万元。",[357,359,361,363],{"key":20,"text":358,"correct":22},"1800",{"key":24,"text":360,"correct":22},"3600",{"key":27,"text":362,"correct":22},"5400",{"key":31,"text":364,"correct":29},"6000",{"id":366,"libraryId":5,"type":15,"typeLabel":16,"stem":367,"options":368,"answer":24,"analysis":33},1107635,"发包人应在收到承包人进度款支付申请后的（ ）天内，根据计量结果和合同约定对申请内容予以核实，确认后向承包人出具进度款支付证书。",[369,370,371,372],{"key":20,"text":51,"correct":22},{"key":24,"text":53,"correct":29},{"key":27,"text":57,"correct":22},{"key":31,"text":173,"correct":22},{"id":374,"libraryId":5,"type":15,"typeLabel":16,"stem":375,"options":376,"answer":20,"analysis":33},1107636,"下列关于工程进度款的说法正确的是（ ）。",[377,379,381,383],{"key":20,"text":378,"correct":29},"进度款支付周期，应与合同约定的工程计量周期一致",{"key":24,"text":380,"correct":22},"按期中结算价款总额计，支付比例不高于60%",{"key":27,"text":382,"correct":22},"进度款支付不用扣除甲供材金额",{"key":31,"text":384,"correct":22},"承包人应在每个计量周期到期后的14天内向发包人提交已完工程进度款申请",{"id":386,"libraryId":5,"type":15,"typeLabel":16,"stem":387,"options":388,"answer":27,"analysis":33},1107637,"某工程合同约定，承包工程合同总额为3000万元，预付款按照合同总额的10%支付，其中主要材料及构件所占比重为60%，工程预付款从未施工工程尚需的主要材料及设备费相当于工程预付款数额时起扣。则该工程的起扣点是（ ）。",[389,391,393,395],{"key":20,"text":390,"correct":22},"300",{"key":24,"text":392,"correct":22},"500",{"key":27,"text":394,"correct":29},"2500",{"key":31,"text":396,"correct":22},"3000",{"id":398,"libraryId":5,"type":15,"typeLabel":16,"stem":399,"options":400,"answer":20,"analysis":33},1107638,"根据《计价规范》的规定，承包人应发包人的要求，采取加快工程进度的措施，使合同工程工期缩短产生的，应由发包人支付的费用，该费用属于（ ）。",[401,403,405,407],{"key":20,"text":402,"correct":29},"提前竣工（赶工）费",{"key":24,"text":404,"correct":22},"施工索赔",{"key":27,"text":406,"correct":22},"误期赔偿费",{"key":31,"text":408,"correct":22},"暂列金额",{"id":410,"libraryId":5,"type":15,"typeLabel":16,"stem":411,"options":412,"answer":31,"analysis":33},1107639,"竣工结算计价时，依据双方确认的工程量和已标价工程量清单的综合单价计算，是指（ ）。",[413,415,417,419],{"key":20,"text":414,"correct":22},"分部分项工程",{"key":24,"text":416,"correct":22},"措施项目",{"key":27,"text":418,"correct":22},"总价措施项目",{"key":31,"text":420,"correct":29},"分部分项工程和单价措施项目",{"id":422,"libraryId":5,"type":15,"typeLabel":16,"stem":423,"options":424,"answer":24,"analysis":33},1107640,"采用工程量清单计价的工程在竣工结算时，暂估价中的工程设备单价，应按（ ）。",[425,427,429,431],{"key":20,"text":426,"correct":22},"承包方自行购买该材料的单价计入综合单价确定",{"key":24,"text":428,"correct":29},"发、承包双方最终确认价在综合单价中调整",{"key":27,"text":430,"correct":22},"招标文件中的暂估价定",{"key":31,"text":432,"correct":22},"市场价格信息在综合单价中调整",{"id":434,"libraryId":5,"type":15,"typeLabel":16,"stem":435,"options":436,"answer":24,"analysis":33},1107641,"某工程分项的清单工程量为1500m3，因变更实际完成工程量为1200m3；该项目的招标控制价的综合单价为400元\u002Fm3，投标报价的综合单价为420元\u002Fm3，投标报价浮动率为5%，则其结算工程款应当为（ ）元。",[437,439,441,443],{"key":20,"text":438,"correct":22},"480000",{"key":24,"text":440,"correct":29},"504000",{"key":27,"text":442,"correct":22},"600000",{"key":31,"text":444,"correct":22},"630000",{"id":446,"libraryId":5,"type":15,"typeLabel":16,"stem":447,"options":448,"answer":24,"analysis":33},1107642,"某工程项目的招标控制价的综合单价为400元\u002Fm3，投标报价的综合单价为320元\u002Fm3，投标报价浮动率为5%。如果履行合同过程中，工程量偏差减少超过15%，则其综合单价应调整为（ ）元\u002Fm3。",[449,450,451,452],{"key":20,"text":146,"correct":22},{"key":24,"text":148,"correct":29},{"key":27,"text":150,"correct":22},{"key":31,"text":152,"correct":22},{"id":454,"libraryId":5,"type":15,"typeLabel":16,"stem":455,"options":456,"answer":27,"analysis":33},1107643,"某混凝土工程招标清单工程量为200m3，综合单价为300元\u002Fm3。在施工过程中，由于工程变更导致实际完成工程量为160 m3。合同约定当实际工程量减少超过15%时可调整单价，调价系数为1.1。该混凝土工程的实际工程费用为（ ）万元。",[457,459,461,463],{"key":20,"text":458,"correct":22},"4.80",{"key":24,"text":460,"correct":22},"4.89",{"key":27,"text":462,"correct":29},"5.28",{"key":31,"text":464,"correct":22},"6.00",{"id":466,"libraryId":5,"type":15,"typeLabel":16,"stem":467,"options":468,"answer":24,"analysis":33},1107644,"投资偏差的原因有多方面的，下列属于设计原因的是（ ）。",[469,471,473,475],{"key":20,"text":470,"correct":22},"设备涨价",{"key":24,"text":472,"correct":29},"图纸提供不及时",{"key":27,"text":474,"correct":22},"未及时提供场地",{"key":31,"text":476,"correct":22},"社会原因",{"id":478,"libraryId":5,"type":15,"typeLabel":16,"stem":479,"options":480,"answer":31,"analysis":33},1107645,"某工程原定2018年9月20日竣工，因承包人原因，致使工程延至2018年10月20日竣工。而且因2018年10月起的法规变化，导致工程造价增加120万元，则该工程的合同价款应（ ）。",[481,483,485,487],{"key":20,"text":482,"correct":22},"调增60万元",{"key":24,"text":484,"correct":22},"调增90万元",{"key":27,"text":486,"correct":22},"调增120万元",{"key":31,"text":488,"correct":29},"不予调整",{"id":490,"libraryId":5,"type":15,"typeLabel":16,"stem":491,"options":492,"answer":24,"analysis":33},1107646,"在工程变更价款的确定中，材料、施工工艺和方法相似，不增加关键线路上工程的施工时间，其项目单价应当（ ）。",[493,495,497,499],{"key":20,"text":494,"correct":22},"直接采用适用项目的单价",{"key":24,"text":496,"correct":29},"参考类似的项目单价，由双方协商确定新的项目单价",{"key":27,"text":498,"correct":22},"采用招标投标时的基础资料和信息价格，按照成本加利润的原则，由双方协商确定新的综合单价",{"key":31,"text":500,"correct":22},"由双方协商确定",{"id":502,"libraryId":5,"type":15,"typeLabel":16,"stem":503,"options":504,"answer":20,"analysis":33},1107647,"根据《建设工程工程量清单计价规范》（GB 50500—2013），工程变更引起施工方案改变并使措施项目发生变化时，承包人提出调整措施项目费用的，应事先将（ ）提交发包人确认。",[505,507,509,511],{"key":20,"text":506,"correct":29},"拟实施的施工方案",{"key":24,"text":508,"correct":22},"索赔意向通知",{"key":27,"text":510,"correct":22},"拟申请增加的费用明细",{"key":31,"text":512,"correct":22},"工程变更的内容",{"id":514,"libraryId":5,"type":15,"typeLabel":16,"stem":515,"options":516,"answer":27,"analysis":33},1107648,"某工程分项的招标工程量清单为1000m2，施工中由于涉及变更实际完成的工程量调整为1200m2。该分项工程招标控制价单价为300元\u002Fm2，投标报价单价为360元\u002Fm2，投标报价浮动率为5%。则根据《计价规范》，该分项工程的超过15%以上部分的单价应为（ ）元\u002Fm2。",[517,519,520,522],{"key":20,"text":518,"correct":22},"242.25",{"key":24,"text":390,"correct":22},{"key":27,"text":521,"correct":29},"345",{"key":31,"text":523,"correct":22},"360",{"id":525,"libraryId":5,"type":15,"typeLabel":16,"stem":526,"options":527,"answer":24,"analysis":33},1107649,"根据《建设工程工程量清单计价规范》（GB 50500－2013），在合同履行期间，由于招标工程量清单缺项，新增了分部分项工程量清单项目，关于其合同价款确定的说法，正确的是（ ）。",[528,530,532,534],{"key":20,"text":529,"correct":22},"新增清单项目的综合单价应当由监理工程师提出",{"key":24,"text":531,"correct":29},"新增清单项目导致新增措施项目的，承包人应将新增措施项目施工方案提交发包人批准",{"key":27,"text":533,"correct":22},"新增清单项目综合单价应由承包人提出，但相关措施项目费用不能再做调整",{"key":31,"text":535,"correct":22},"新增清单项目应当额外工程处理，承包人可选择或者不做",{"id":537,"libraryId":5,"type":15,"typeLabel":16,"stem":538,"options":539,"answer":27,"analysis":33},1107651,"施工过程中，发包人要求提前竣工并征得承包人同意、商定相关措施、修订进度计划后，其提前竣工或赶工补偿费用，不包括（ ）。",[540,542,544,546],{"key":20,"text":541,"correct":22},"新增加投入人工的报酬",{"key":24,"text":543,"correct":22},"不经济使用人工和机械而增加的费用",{"key":27,"text":545,"correct":29},"赶工引起的企业管理费增加",{"key":31,"text":547,"correct":22},"材料提前交货可能增加的费用以及材料运输费的增加",{"id":549,"libraryId":5,"type":15,"typeLabel":16,"stem":550,"options":551,"answer":27,"analysis":33},1107652,"某工程分项所采用的甲种材料的施工期间实际单价、基准单价、投标单价依次为424元\u002Fm2、400元\u002Fm2、380元\u002Fm2，若风险系数为5%。则调整后的综合单价为（ ）元\u002Fm2。",[552,553,555,557],{"key":20,"text":150,"correct":22},{"key":24,"text":554,"correct":22},"390",{"key":27,"text":556,"correct":29},"384",{"key":31,"text":558,"correct":22},"380",{"id":560,"libraryId":5,"type":15,"typeLabel":16,"stem":561,"options":562,"answer":20,"analysis":33},1107653,"投资偏差分析的赢得值法中，已完工作预算投资（BCWP）是指（ ）。",[563,565,567,569],{"key":20,"text":564,"correct":29},"已完成工作量×预算单价",{"key":24,"text":566,"correct":22},"计划工作量×预算单价",{"key":27,"text":568,"correct":22},"已完成工作量×实际单价",{"key":31,"text":570,"correct":22},"计划工作量×实际单价",{"id":572,"libraryId":5,"type":15,"typeLabel":16,"stem":573,"options":574,"answer":20,"analysis":33},1107654,"某钢筋混凝土结构分项工程，某月份的计划单价和计划工程量分别为350元\u002Fm3和3000m3，该月份的实际单价和实际完成工程量分别为360元\u002Fm3和3200m3。则利用赢得值法计算出的该月份混凝土工程的投资偏差和进度偏差分别为（ ）万元。",[575,577,579,581],{"key":20,"text":576,"correct":29},"超支3.2万元、超前7万元",{"key":24,"text":578,"correct":22},"超支3.2万元、拖后7万元",{"key":27,"text":580,"correct":22},"节约3.2万元、拖后3万元",{"key":31,"text":582,"correct":22},"节约3.2万元、超前3万元",{"id":584,"libraryId":5,"type":15,"typeLabel":16,"stem":585,"options":586,"answer":24,"analysis":33},1107656,"根据现行规定，工程预付工程款的额度最高不得超过（ ）。",[587,589,591,593],{"key":20,"text":588,"correct":22},"合同金额（扣除暂列金额）的20%",{"key":24,"text":590,"correct":29},"合同金额（扣除暂列金额）的30%",{"key":27,"text":592,"correct":22},"合同金额（不扣除暂列金额）的20%",{"key":31,"text":594,"correct":22},"合同金额（不扣除暂列金额）的30%",{"id":596,"libraryId":5,"type":15,"typeLabel":16,"stem":597,"options":598,"answer":31,"analysis":33},1107657,"根据《建设工程工程量清单计价规范》（GB 50500—2013），签约合同中的暂估材料在确定单价以后，其相应项目综合单价的处理方式是（ ）。",[599,601,603,605],{"key":20,"text":600,"correct":22},"在综合单价中用确定单价代替原暂估价，并调整企业管理费，不调整利润",{"key":24,"text":602,"correct":22},"在综合单价中用确定单价代替原暂估价，并调整企业管理费和利润",{"key":27,"text":604,"correct":22},"综合单价不做调整",{"key":31,"text":606,"correct":29},"在综合单价中用确定单价代替原暂估价，不涉及企业管理费和利润",[608,611,614,617,620,623],{"id":15,"name":609,"category":7,"favorite":610},"领导干部任职前廉政法规知识测试题",92,{"id":612,"name":613,"category":7,"favorite":15},595,"建筑结构与设备",{"id":615,"name":616,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":618,"name":619,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":621,"name":622,"category":7,"favorite":8},534,"BIM工程师",{"id":624,"name":622,"category":7,"favorite":8},535]