[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-783-13":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":572},{"id":5,"name":6,"category":7,"favorite":8},783,"目标控制（土木建筑）","建筑工程",0,13,50,2641,[13,34,46,57,69,81,92,104,116,128,140,152,161,173,185,197,209,221,233,245,257,269,281,293,305,315,327,339,348,360,369,381,393,403,413,421,432,440,452,463,474,482,494,506,514,526,536,547,555,563],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":20,"analysis":33},1107810,1,"单选题","对受委托编制的工程量清单，应有造价工程师签字、盖章，还应有（ ）。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","造价咨询人盖章",true,{"key":24,"text":25,"correct":26},"B","招标单位法定代表人盖章",false,{"key":28,"text":29,"correct":26},"C","编制人盖章",{"key":31,"text":32,"correct":26},"D","负责审核的造价工程师盖章","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":28,"analysis":33},1107811,"根据《建设工程工程量清单计价规范》GB 50500－2013的规定，在合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的零星额外工作应列入（ ）中。",[38,40,42,44],{"key":20,"text":39,"correct":26},"暂估价",{"key":24,"text":41,"correct":26},"暂列金额",{"key":28,"text":43,"correct":22},"计日工",{"key":31,"text":45,"correct":26},"措施项目费",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},1107812,"根据《建设工程工程量清单计价规范》GB 50500－2013的规定，在其他项目清单中应包括（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":26},"环境保护费",{"key":24,"text":53,"correct":26},"夜间施工费",{"key":28,"text":55,"correct":26},"施工排水费",{"key":31,"text":39,"correct":22},{"id":58,"libraryId":5,"type":15,"typeLabel":16,"stem":59,"options":60,"answer":20,"analysis":33},1107813,"根据《建设工程工程量清单计价规范》GB 50500－2013的规定，下列费用中应列入其他项目清单的是（ ）。",[61,63,65,67],{"key":20,"text":62,"correct":22},"总承包服务费",{"key":24,"text":64,"correct":26},"安全文明施工费",{"key":28,"text":66,"correct":26},"二次搬运费",{"key":31,"text":68,"correct":26},"夜间施工增加费",{"id":70,"libraryId":5,"type":15,"typeLabel":16,"stem":71,"options":72,"answer":31,"analysis":33},1107814,"下列设计方案评价方法中，属于定性评价的是（ ）。",[73,75,77,79],{"key":20,"text":74,"correct":26},"比较价值评分法",{"key":24,"text":76,"correct":26},"加权评分法",{"key":28,"text":78,"correct":26},"定性评价定量化",{"key":31,"text":80,"correct":22},"优缺点列举法",{"id":82,"libraryId":5,"type":15,"typeLabel":16,"stem":83,"options":84,"answer":28,"analysis":33},1107815,"方案综合评价的基本方法包括定性评价法和定量评价法，下列属于定量评价法的是（ ）。",[85,86,88,90],{"key":20,"text":80,"correct":26},{"key":24,"text":87,"correct":26},"德尔菲法",{"key":28,"text":89,"correct":22},"环比评分法",{"key":31,"text":91,"correct":26},"强制列举法",{"id":93,"libraryId":5,"type":15,"typeLabel":16,"stem":94,"options":95,"answer":20,"analysis":33},1107816,"进行产品价值工程分析活动中，产品按功能分为甲、乙、丙、丁四种零部件，分析得到其价值系数分别为0.6、0.9、1、1.3。则从价值工程的角度分析该产品应优先改进的零部件是（ ）。",[96,98,100,102],{"key":20,"text":97,"correct":22},"甲",{"key":24,"text":99,"correct":26},"乙",{"key":28,"text":101,"correct":26},"丙",{"key":31,"text":103,"correct":26},"丁",{"id":105,"libraryId":5,"type":15,"typeLabel":16,"stem":106,"options":107,"answer":24,"analysis":33},1107817,"某产品的目标成本为2000元。该产品某零部件的功能重要性系数是0.28，若现实成本为700元，则该零部件成本需要降低（ ）元。",[108,110,112,114],{"key":20,"text":109,"correct":26},"120",{"key":24,"text":111,"correct":22},"140",{"key":28,"text":113,"correct":26},"180",{"key":31,"text":115,"correct":26},"210",{"id":117,"libraryId":5,"type":15,"typeLabel":16,"stem":118,"options":119,"answer":20,"analysis":33},1107819,"价值工程的核心是（ ）。",[120,122,124,126],{"key":20,"text":121,"correct":22},"对产品进行功能分析",{"key":24,"text":123,"correct":26},"对产品进行价值分析",{"key":28,"text":125,"correct":26},"寻求最低的寿命周期成本",{"key":31,"text":127,"correct":26},"寻求最低的项目运行成本",{"id":129,"libraryId":5,"type":15,"typeLabel":16,"stem":130,"options":131,"answer":31,"analysis":33},1107820,"在选择价值工程研究对象时，应遵循的原则是（ ）。",[132,134,136,138],{"key":20,"text":133,"correct":26},"在设计方面，应选择结构较简单的产品",{"key":24,"text":135,"correct":26},"在生产方面，应选择废品率较低的产品",{"key":28,"text":137,"correct":26},"在销售方面，应选择竞争力高于同类产品.寿命周期短的产品",{"key":31,"text":139,"correct":22},"在成本方面，应选择成本高于同类产品.成本比重大的产品",{"id":141,"libraryId":5,"type":15,"typeLabel":16,"stem":142,"options":143,"answer":24,"analysis":33},1107821,"以“关键的少数和次要的多数”为原理，应用数理统计分析的方法来选择对象的方法称为（ ）。",[144,146,148,150],{"key":20,"text":145,"correct":26},"因素分析法",{"key":24,"text":147,"correct":22},"ABC分析法",{"key":28,"text":149,"correct":26},"强制确定法",{"key":31,"text":151,"correct":26},"价值指数法",{"id":153,"libraryId":5,"type":15,"typeLabel":16,"stem":154,"options":155,"answer":28,"analysis":33},1107822,"以功能重要程度作为选择价值工程对象的一种分析方法是（ ）。",[156,157,159,160],{"key":20,"text":145,"correct":26},{"key":24,"text":158,"correct":26},"重点选择法",{"key":28,"text":149,"correct":22},{"key":31,"text":151,"correct":26},{"id":162,"libraryId":5,"type":15,"typeLabel":16,"stem":163,"options":164,"answer":24,"analysis":33},1107823,"其正确顺序是（ ）。",[165,167,169,171],{"key":20,"text":166,"correct":26},"③—①—②—④",{"key":24,"text":168,"correct":22},"①—③—②—④",{"key":28,"text":170,"correct":26},"③—②—①—④",{"key":31,"text":172,"correct":26},"①—②—③—④",{"id":174,"libraryId":5,"type":15,"typeLabel":16,"stem":175,"options":176,"answer":28,"analysis":33},1107824,"设计概算一经批准一般不得进行调整，其总投资反映（ ）时的价格水平。",[177,179,181,183],{"key":20,"text":178,"correct":26},"项目立项",{"key":24,"text":180,"correct":26},"可行性研究",{"key":28,"text":182,"correct":22},"概算编制",{"key":31,"text":184,"correct":26},"项目施工",{"id":186,"libraryId":5,"type":15,"typeLabel":16,"stem":187,"options":188,"answer":31,"analysis":33},1107825,"下列设计概算中，属于单位建筑工程概算的是（ ）。",[189,191,193,195],{"key":20,"text":190,"correct":26},"机械设备及安装工程概算",{"key":24,"text":192,"correct":26},"电气设备及安装工程概算",{"key":28,"text":194,"correct":26},"工器具及生产家具购置费用概算",{"key":31,"text":196,"correct":22},"通风工程概算",{"id":198,"libraryId":5,"type":15,"typeLabel":16,"stem":199,"options":200,"answer":24,"analysis":33},1107826,"下列属于审查设计概算的编制依据的是（ ）。",[201,203,205,207],{"key":20,"text":202,"correct":26},"盈利性审查",{"key":24,"text":204,"correct":22},"时效性审查",{"key":28,"text":206,"correct":26},"公益性审查",{"key":31,"text":208,"correct":26},"准确性审查",{"id":210,"libraryId":5,"type":15,"typeLabel":16,"stem":211,"options":212,"answer":20,"analysis":33},1107827,"在设备安装工程概算编制的方法中，计算比较具体，精确性较高的方法是（ ）。",[213,215,217,219],{"key":20,"text":214,"correct":22},"预算单价法",{"key":24,"text":216,"correct":26},"扩大单价法",{"key":28,"text":218,"correct":26},"净概算指标法",{"key":31,"text":220,"correct":26},"百分比分析法",{"id":222,"libraryId":5,"type":15,"typeLabel":16,"stem":223,"options":224,"answer":28,"analysis":33},1107828,"实物量法编制单位工程施工图预算所用的材料单价应采用（ ）。",[225,227,229,231],{"key":20,"text":226,"correct":26},"网上咨询厂家的报价",{"key":24,"text":228,"correct":26},"编制预算定额时采用的单价",{"key":28,"text":230,"correct":22},"当时当地的实际价格",{"key":31,"text":232,"correct":26},"预算定额中采用的单价加上运杂费",{"id":234,"libraryId":5,"type":15,"typeLabel":16,"stem":235,"options":236,"answer":24,"analysis":33},1107829,"实物量法编制施工图预算时，计算工程量后紧接着进行的工作是（ ）。",[237,239,241,243],{"key":20,"text":238,"correct":26},"套定额单价，计算人材机费用",{"key":24,"text":240,"correct":22},"套消耗定额，计算人材机消耗量",{"key":28,"text":242,"correct":26},"汇总人材机费用",{"key":31,"text":244,"correct":26},"计算管理费等其他各项费用",{"id":246,"libraryId":5,"type":15,"typeLabel":16,"stem":247,"options":248,"answer":24,"analysis":33},1107830,"根据施工图预算文件的编制形式，二级预算编制的组成中应包括（ ）。",[249,251,253,255],{"key":20,"text":250,"correct":26},"单项工程预算表",{"key":24,"text":252,"correct":22},"总预算表",{"key":28,"text":254,"correct":26},"综合预算表",{"key":31,"text":256,"correct":26},"编制依据",{"id":258,"libraryId":5,"type":15,"typeLabel":16,"stem":259,"options":260,"answer":28,"analysis":33},1107831,"审查住宅工程和不具备全面审查条件的工程，应采用（ ）。",[261,263,265,267],{"key":20,"text":262,"correct":26},"全面审查法",{"key":24,"text":264,"correct":26},"标准预算审查法",{"key":28,"text":266,"correct":22},"筛选审查法",{"key":31,"text":268,"correct":26},"重点审查法",{"id":270,"libraryId":5,"type":15,"typeLabel":16,"stem":271,"options":272,"answer":20,"analysis":33},1107832,"下列各项中，属于施工图预算对发包人作用的是（ ）。",[273,275,277,279],{"key":20,"text":274,"correct":22},"施工图预算是施工图设计阶段确定建设项目造价的依据",{"key":24,"text":276,"correct":26},"施工图预算是控制施工成本的依据",{"key":28,"text":278,"correct":26},"施工图预算是仲裁.管理.司法机关在处理合同经济纠纷时的重要依据",{"key":31,"text":280,"correct":26},"施工图预算是承包人进行施工准备的依据",{"id":282,"libraryId":5,"type":15,"typeLabel":16,"stem":283,"options":284,"answer":24,"analysis":33},1107833,"某建设项目工程费用6800万元，其他费用1200万元，预备费500万元，建设期贷款利息370万元，铺底流动资金710万元。预计在建设中原房屋拆除变现收入100万元，试车收入大于支出金额150万元，则该项目总预算为（ ）万元。",[285,287,289,291],{"key":20,"text":286,"correct":26},"9580",{"key":24,"text":288,"correct":22},"9330",{"key":28,"text":290,"correct":26},"9680",{"key":31,"text":292,"correct":26},"9430",{"id":294,"libraryId":5,"type":15,"typeLabel":16,"stem":295,"options":296,"answer":20,"analysis":33},1107834,"某工程设计有四个备选方案，经论证，四个方案的功能得分和单方造价如下表。按照价值工程原理，应选择的最优方案是（ ）。",[297,299,301,303],{"key":20,"text":298,"correct":22},"甲方案",{"key":24,"text":300,"correct":26},"乙方案",{"key":28,"text":302,"correct":26},"丙方案",{"key":31,"text":304,"correct":26},"丁方案",{"id":306,"libraryId":5,"type":15,"typeLabel":16,"stem":307,"options":308,"answer":31,"analysis":33},1107835,"在新方案创造中，组织者将问题函寄专家后获得反馈意见，整理分析后再函寄，直到得出新方案。这属于（ ）。",[309,310,312,314],{"key":20,"text":149,"correct":26},{"key":24,"text":311,"correct":26},"头脑风暴法",{"key":28,"text":313,"correct":26},"哥顿法",{"key":31,"text":87,"correct":22},{"id":316,"libraryId":5,"type":15,"typeLabel":16,"stem":317,"options":318,"answer":28,"analysis":33},1107837,"在设计概算文件的编制形式中，二级概算编制的组成，不应包括（ ）。",[319,321,323,325],{"key":20,"text":320,"correct":26},"编制说明",{"key":24,"text":322,"correct":26},"总概算表",{"key":28,"text":324,"correct":22},"综合概算表",{"key":31,"text":326,"correct":26},"单位工程概算表",{"id":328,"libraryId":5,"type":15,"typeLabel":16,"stem":329,"options":330,"answer":28,"analysis":33},1107838,"在采用定额单价法编制施工图预算的过程中，套用定额单价时，发现分析工程施工工艺条件与预算单价不一致，则应当（ ）。",[331,333,335,337],{"key":20,"text":332,"correct":26},"直接套用",{"key":24,"text":334,"correct":26},"换算预算价格",{"key":28,"text":336,"correct":22},"调量不调价",{"key":31,"text":338,"correct":26},"编制补充单位估价表",{"id":340,"libraryId":5,"type":15,"typeLabel":16,"stem":341,"options":342,"answer":28,"analysis":33},1107839,"根据施工图预算文件的编制形式，二级预算编制的组成中，不应包括（ ）。",[343,344,345,346],{"key":20,"text":320,"correct":26},{"key":24,"text":252,"correct":26},{"key":28,"text":254,"correct":22},{"key":31,"text":347,"correct":26},"单位工程预算表",{"id":349,"libraryId":5,"type":15,"typeLabel":16,"stem":350,"options":351,"answer":20,"analysis":33},1107840,"关于施工图预算编制内容和要求的说法，正确的是（ ）。",[352,354,356,358],{"key":20,"text":353,"correct":22},"施工图总预算应控制在已批准的设计总概算投资范围以内",{"key":24,"text":355,"correct":26},"当建设项目只有一个单项工程时，则不需要编制建设项目总预算",{"key":28,"text":357,"correct":26},"单位工程预算编制依据的定额应为企业定额",{"key":31,"text":359,"correct":26},"建设项目总预算是反映建设项目施工阶段投资总额的造价文件",{"id":361,"libraryId":5,"type":15,"typeLabel":16,"stem":362,"options":363,"answer":20,"analysis":33},1107841,"对于设计方案比较特殊，无同类工程可比，且审查精度要求高的施工图预算，适宜采用的审查方法是（ ）。",[364,365,366,368],{"key":20,"text":262,"correct":22},{"key":24,"text":264,"correct":26},{"key":28,"text":367,"correct":26},"对比审查法",{"key":31,"text":268,"correct":26},{"id":370,"libraryId":5,"type":15,"typeLabel":16,"stem":371,"options":372,"answer":31,"analysis":33},1107842,"实物量法与预算单价法编制施工图预算的主要区别是（ ）。",[373,375,377,379],{"key":20,"text":374,"correct":26},"收集的资料不同",{"key":24,"text":376,"correct":26},"工程量计算规则不同",{"key":28,"text":378,"correct":26},"采用的定额不同",{"key":31,"text":380,"correct":22},"计算工料机费用的方法不同",{"id":382,"libraryId":5,"type":15,"typeLabel":16,"stem":383,"options":384,"answer":24,"analysis":33},1107844,"审查设计概算时，通常采用（ ）的审查方式。",[385,387,389,391],{"key":20,"text":386,"correct":26},"标准审查",{"key":24,"text":388,"correct":22},"集中会审",{"key":28,"text":390,"correct":26},"对比分析",{"key":31,"text":392,"correct":26},"查询核实",{"id":394,"libraryId":5,"type":15,"typeLabel":16,"stem":395,"options":396,"answer":24,"analysis":33},1107845,"某住宅工程项目设计深度不够，其结构特征与概算指标的结构特征局部有差别，编制设计概算时，宜采用的方法是（ ）。",[397,398,400,402],{"key":20,"text":216,"correct":26},{"key":24,"text":399,"correct":22},"修正的概算指标法",{"key":28,"text":401,"correct":26},"概算指标法",{"key":31,"text":214,"correct":26},{"id":404,"libraryId":5,"type":15,"typeLabel":16,"stem":405,"options":406,"answer":31,"analysis":33},1107846,"下列单项工程综合概算中，属于设备及安装工程概算的是（ ）。",[407,408,410,412],{"key":20,"text":196,"correct":26},{"key":24,"text":409,"correct":26},"电气照明工程概算",{"key":28,"text":411,"correct":26},"采暖工程概算",{"key":31,"text":194,"correct":22},{"id":414,"libraryId":5,"type":15,"typeLabel":16,"stem":415,"options":416,"answer":28,"analysis":33},1107847,"根据功能重要程度选择价值工程对象的方法称为（ ）。",[417,418,419,420],{"key":20,"text":145,"correct":26},{"key":24,"text":147,"correct":26},{"key":28,"text":149,"correct":22},{"key":31,"text":151,"correct":26},{"id":422,"libraryId":5,"type":15,"typeLabel":16,"stem":423,"options":424,"answer":20,"analysis":33},1107848,"某产品的目标成本为2000元。该产品某零部件的功能重要性系数是0.32，若现实成本为800元，则该零部件成本需要降低（ ）元。",[425,427,428,430],{"key":20,"text":426,"correct":22},"160",{"key":24,"text":115,"correct":26},{"key":28,"text":429,"correct":26},"230",{"key":31,"text":431,"correct":26},"240",{"id":433,"libraryId":5,"type":15,"typeLabel":16,"stem":434,"options":435,"answer":24,"analysis":33},1107849,"根据计算，应优先选择分部工程（ ）为价值工程对象。",[436,437,438,439],{"key":20,"text":97,"correct":26},{"key":24,"text":99,"correct":22},{"key":28,"text":101,"correct":26},{"key":31,"text":103,"correct":26},{"id":441,"libraryId":5,"type":15,"typeLabel":16,"stem":442,"options":443,"answer":31,"analysis":33},1107851,"价值工程中的全寿命周期费用是指（ ）。",[444,446,448,450],{"key":20,"text":445,"correct":26},"生产过程发生的全部成本",{"key":24,"text":447,"correct":26},"从开始使用至报废过程中发生的费用总和",{"key":28,"text":449,"correct":26},"产品存续期的总成本",{"key":31,"text":451,"correct":22},"生产费用、使用费用之和",{"id":453,"libraryId":5,"type":15,"typeLabel":16,"stem":454,"options":455,"answer":20,"analysis":33},1107852,"开展价值工程活动的目的是（ ）。",[456,458,460,462],{"key":20,"text":457,"correct":22},"提高研究对象的价值",{"key":24,"text":459,"correct":26},"实现使用者需要的功能",{"key":28,"text":461,"correct":26},"降低产品的寿命周期成本",{"key":31,"text":121,"correct":26},{"id":464,"libraryId":5,"type":15,"typeLabel":16,"stem":465,"options":466,"answer":24,"analysis":33},1107853,"功能价值的计算方法包括功能指数法和（ ）。",[467,468,470,472],{"key":20,"text":313,"correct":26},{"key":24,"text":469,"correct":22},"功能成本法",{"key":28,"text":471,"correct":26},"专家检查法",{"key":31,"text":473,"correct":26},"专家意见法",{"id":475,"libraryId":5,"type":15,"typeLabel":16,"stem":476,"options":477,"answer":20,"analysis":33},1107854,"（ ）又称重点选择法或不均匀分布定律法，是指应用数理统计分析的方法来选择对象的一种方法。",[478,479,480,481],{"key":20,"text":147,"correct":22},{"key":24,"text":149,"correct":26},{"key":28,"text":145,"correct":26},{"key":31,"text":151,"correct":26},{"id":483,"libraryId":5,"type":15,"typeLabel":16,"stem":484,"options":485,"answer":31,"analysis":33},1107855,"某工程有4个设计方案，方案一的功能系数为0.61，成本系数为0.55；方案二的功能系数为0.63，成本系数为0.6；方案三的功能系数为0.62，成本系数为0.57；方案四的功能系数为0.64，成本系数为0.56。根据价值工程原理确定的最优方案为（ ）。",[486,488,490,492],{"key":20,"text":487,"correct":26},"方案一",{"key":24,"text":489,"correct":26},"方案二",{"key":28,"text":491,"correct":26},"方案三",{"key":31,"text":493,"correct":22},"方案四",{"id":495,"libraryId":5,"type":15,"typeLabel":16,"stem":496,"options":497,"answer":24,"analysis":33},1107856,"下列有关价值工程中，功能价值分析的说法中，正确的是（ ）。",[498,500,502,504],{"key":20,"text":499,"correct":26},"在功能成本法中，V＞1即功能现实成本大于功能评价值",{"key":24,"text":501,"correct":22},"在功能成本法中，V＜1时，可能存在功能过剩",{"key":28,"text":503,"correct":26},"在价值指数法中，V＞1时，一般都要列入改进对象",{"key":31,"text":505,"correct":26},"在价值指数法中，V＞1即评价对象成本大于功能比重",{"id":507,"libraryId":5,"type":15,"typeLabel":16,"stem":508,"options":509,"answer":20,"analysis":33},1107857,"依据分析人员经验做出选择，简便易行，在被研究对象彼此相差比较大以及时间紧迫的情况下比较适用的定性分析方法是（ ）。",[510,511,512,513],{"key":20,"text":145,"correct":22},{"key":24,"text":147,"correct":26},{"key":28,"text":149,"correct":26},{"key":31,"text":151,"correct":26},{"id":515,"libraryId":5,"type":15,"typeLabel":16,"stem":516,"options":517,"answer":24,"analysis":33},1107858,"在价值工程一般工作程序中，功能评价是属于（ ）的工作内容。",[518,520,522,524],{"key":20,"text":519,"correct":26},"准备阶段",{"key":24,"text":521,"correct":22},"分析阶段",{"key":28,"text":523,"correct":26},"创新阶段",{"key":31,"text":525,"correct":26},"实施阶段",{"id":527,"libraryId":5,"type":15,"typeLabel":16,"stem":528,"options":529,"answer":20,"analysis":33},1107859,"下列选项中，属于在设计方案评选之初，对设计方案所采取的定量评价法的是（ ）。",[530,532,534,535],{"key":20,"text":531,"correct":22},"经济效果评价法",{"key":24,"text":533,"correct":26},"直接评分法",{"key":28,"text":76,"correct":26},{"key":31,"text":80,"correct":26},{"id":537,"libraryId":5,"type":15,"typeLabel":16,"stem":538,"options":539,"answer":28,"analysis":33},1107860,"在设计概算的编制中，概算编制说明应该包括的是（ ）。",[540,542,544,546],{"key":20,"text":541,"correct":26},"施工单位",{"key":24,"text":543,"correct":26},"图纸说明书",{"key":28,"text":545,"correct":22},"主要技术经济指标",{"key":31,"text":322,"correct":26},{"id":548,"libraryId":5,"type":15,"typeLabel":16,"stem":549,"options":550,"answer":24,"analysis":33},1107861,"利用扩大单价法编制单位建筑工程概算时，在收集原始资料后，应进行的工作有：①计算工程量；②各项费用计算；③套用扩大单价；④计算单位工程概算造价。其正确顺序是（ ）。",[551,552,553,554],{"key":20,"text":166,"correct":26},{"key":24,"text":168,"correct":22},{"key":28,"text":170,"correct":26},{"key":31,"text":172,"correct":26},{"id":556,"libraryId":5,"type":15,"typeLabel":16,"stem":557,"options":558,"answer":31,"analysis":33},1107862,"当初步设计有详细设备清单时，编制设备安装工程概算中，精确性较高的方法是（ ）。",[559,560,561,562],{"key":20,"text":216,"correct":26},{"key":24,"text":401,"correct":26},{"key":28,"text":399,"correct":26},{"key":31,"text":214,"correct":22},{"id":564,"libraryId":5,"type":15,"typeLabel":16,"stem":565,"options":566,"answer":24,"analysis":33},1107863,"住宅或投资额较少的建设项目，其建筑工程概算宜采用（ ）编制。",[567,568,569,570],{"key":20,"text":216,"correct":26},{"key":24,"text":401,"correct":22},{"key":28,"text":214,"correct":26},{"key":31,"text":571,"correct":26},"投资估算法",[573,576,579,582,585,588],{"id":15,"name":574,"category":7,"favorite":575},"领导干部任职前廉政法规知识测试题",92,{"id":577,"name":578,"category":7,"favorite":15},595,"建筑结构与设备",{"id":580,"name":581,"category":7,"favorite":15},715,"招标采购专业知识与法律法规",{"id":583,"name":584,"category":7,"favorite":15},848,"市政方向-通用基础",{"id":586,"name":587,"category":7,"favorite":8},534,"BIM工程师",{"id":589,"name":587,"category":7,"favorite":8},535]