[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110158,783,1,"单选题","关于PPP项目实施过程中的风险分配的说法，错误的是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目设计、建造、财务和运营维护等商业风险由社会资本承担",false,{"key":16,"text":17,"correct":18},"B","不可抗力风险由政府承担",true,{"key":20,"text":21,"correct":14},"C","法律、政策的风险由政府承担",{"key":23,"text":24,"correct":14},"D","最低需求的风险由政府承担","2020版教材P52-63 按照风险分配优化、风险收益对等和风险可控等原则，综合考虑政府风险管理能力、项目回报机制和市场风险管理能力等要素，在政府和社会资本间合理分配项目风险。原则上，项目设计、建造、财务和运营维护等商业风险由社会资本承担，法律、政策和最低需求等风险由政府承担，不可抗力等风险由政府和社会资本合理共担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]