[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110156":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110156,783,1,"单选题","在PPP项目实施方案中，( )主要明确项目资产权属、社会资本承担的公共责任、政府支付方式和风险分配结果等。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","权利义务边界",true,{"key":16,"text":17,"correct":18},"B","交易条件边界",false,{"key":20,"text":21,"correct":18},"C","履约保障边界",{"key":23,"text":24,"correct":18},"D","调整衔接边界","2020版教材P52-63 本题考查的是项目融资的主要方式。权利义务边界主要明确项目资产权属、社会资本承担的公共责任、政府支付方式和风险分配结果等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]