[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110084":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110084,783,1,"单选题","（2019年真题）某新建项目，建设期2年，第1年向银行借款2000万元，第2年向银行借款3000万元，年利率为6%，则该项目估算的建设期利息为（ ）万元。 A.213.6",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","247.2",false,{"key":16,"text":17,"correct":14},"B","]",{"key":19,"text":20,"correct":21},"C","273.6",true,{"key":23,"text":24,"correct":14},"D","427.2","本题考查的是建设期利息。第1年应计利息=2000\u002F2×6%=60（万元）；第2年应计利息=（2000+60+3000\u002F2）×6%=213.6（万元）；建设期贷款利息=60+213.6=273.6（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]