[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110067,783,1,"单选题","已知某项目建筑安装工程费为2000万元，设备购置费3000万元，工程建设其他费1000万元，若基本预备费费率为10％，项目建设前期为2年，建设期为3年，各年投资计划额为：第一年完成投资20％，其余投资在后两年平均投入，年均价格上涨率为5％，则该项目建设期间涨价预备费为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","575.53",false,{"key":16,"text":17,"correct":14},"B","648.18",{"key":19,"text":20,"correct":14},"C","752.73",{"key":22,"text":23,"correct":24},"D","1311.02",true,"2020版教材P35-36 静态投资=(2000+3000+1000)×(1+10％)=6600(万元) 2020版教材PF1=6600×20％×[(1+5％)2.5-1]=171.24(万元) 2020版教材PF2=6600×40％×[(1+5％)3.5-1]=491.60(万元) 2020版教材PF3=6600×40％×[(1+5％)4.5-1]=648.18(万元) 涨价预备费=171.24+491.60+648.18=1311.02(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]