[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110063,783,1,"单选题","某建设项目工程费用为7000万元，工程建设其他费用为2000万元，基本预备费为500万元。项目前期年限1年，建设期2年，各年度完成静态投资额的比例分别为60％与40％，年均投资价格上涨率为6％。则该项目建设期第二年价差预备费为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","444.96",false,{"key":16,"text":17,"correct":14},"B","451.63",{"key":19,"text":20,"correct":14},"C","564.54",{"key":22,"text":23,"correct":24},"D","595.90",true,"2020版教材P35-36 建设期第二年的静态投资计划额=(7000+2000+500)×40％=3800(万元)； 第二年的涨价预备费=3800 ×[(1+6％)1(1+6％)0.5(1+6％)1-1]=595.90(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]