[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110059,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500—2013），分部分项工程清单综合单价应包含（）以及一定范围内的风险费用",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费、材料费、施工机具使用费、企业管理费、利润",true,{"key":16,"text":17,"correct":18},"B","人工费、材料费、施工机具使用费、企业管理费、规费",false,{"key":20,"text":21,"correct":18},"C","人工费、材料费、施工机具使用费、规费、利润、税金",{"key":23,"text":24,"correct":18},"D","材料费、工程设备费、施工机具使用费、规费、税金、企业管理费","2020版教材P19-23 综合单价包括人工费、材料费、施工机具使用费、企业管理费和利润以及一定范围的风险费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]