[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110058,783,1,"单选题","某建设项目，建设期为2年，其向银行贷款1200万元，贷款时间和额度为第1年600万元，第2年600万元，贷款年利率6％，则该项目的建设期利息为（）万元",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","54",false,{"key":16,"text":17,"correct":14},"B","55.08",{"key":19,"text":20,"correct":14},"C","72",{"key":22,"text":23,"correct":24},"D","73.08",true,"2020版教材P36 根据建设期利息的计算公式，该项目贷款第一年应计利息=600×1／2×6％=18(万元)，第二年应计利息=(600+18+600×1／2)×6％=55.08(万元)。因此，建设期利息=18+55.08=73.08(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]