[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110046,783,1,"单选题","建设项目竣工验收前，施工企业对已完工程进行保护发生的费用应计入( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目费",true,{"key":16,"text":17,"correct":18},"B","规费",false,{"key":20,"text":21,"correct":18},"C","分部分项工程费",{"key":23,"text":24,"correct":18},"D","企业管理费","2020版教材P17-19 措施项目费包括安全文明施工费、夜间施工增加费、二次搬运费、冬雨期施工增加费、已完工程及设备保护费、工程定位复测费、特殊地区施工增加费、大型机械设备进出场及安拆费、脚手架工程费。其中，已完工程及设备保护费指竣工验收前，对已完工程及设备采取的必要保护措施所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]