[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110045,783,1,"单选题","某施工企业为了提高混凝土强度并加快模板的周转速度，在混凝土中加入了经试验后满足上述要求的一种外加剂。该外加剂的费用属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费",false,{"key":16,"text":17,"correct":18},"B","材料费",true,{"key":20,"text":21,"correct":14},"C","检验试验费",{"key":23,"text":24,"correct":14},"D","研究试验费","2020版教材P13-17 材料费是指施工过程中耗费的原材料、辅助材料、构配件、零件、半成品或成品、工程设备的费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]