[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110044,783,1,"单选题","世界银行和国际咨询工程师联合会对项目的总建设成本做了统一规定，内容包括四个部分：项目直接建设成本、项目间接建设成本、（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","未明确项目的准备金和建设成本上升费用",false,{"key":16,"text":17,"correct":14},"B","基本预备费和涨价预备费",{"key":19,"text":20,"correct":21},"C","应急费和建设成本上升费用",true,{"key":23,"text":24,"correct":14},"D","来明确项目的准备金和不可预见准备金","2020版教材P11-13 世界银行、国际咨询工程师联合会对项目的总建设成本作了统一规定，包括项目直接建设成本、项目间接建设成本、应急费及建设成本上升费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]