[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1110031,783,1,"单选题","世界银行规定的项目总建设成本中，下列（ ）不是其组成部分。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应急费用",false,{"key":16,"text":17,"correct":14},"B","项目间接建设成本",{"key":19,"text":20,"correct":21},"C","估算误差费用补偿",true,{"key":23,"text":24,"correct":14},"D","建设成本上升费用","2020版教材P11 本题考查的是世界银行规定的建设项目总投资构成。这包括项目直接建设成本、项目间接建设成本、项目应急费用及建设成本上升费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]