[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110028,783,1,"单选题","生产单位提前进厂参加施工、设备安装、调试的人员，其工资、工资性补贴等费用应从（ ）中支付。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建筑安装工程费",false,{"key":16,"text":17,"correct":14},"B","设备及工、器具购置费",{"key":19,"text":20,"correct":14},"C","建设单位管理费",{"key":22,"text":23,"correct":24},"D","生产准备费",true,"2020版教材P35 本题考查的是生产准备费的费用内容。包括：生产单位提前进厂参加施工、设备安装、调试等以及熟悉工艺流程及设备性能等人员的工资、工资性补贴、职工福利费、差旅交通费、劳动保护费等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]