[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110026":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1110026,783,1,"单选题","某新建项目，建设期为2年，共从银行贷款960万元，每年贷款额相等。贷款年利率为6%，则该项目建设期利息为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","44.06",false,{"key":16,"text":17,"correct":18},"B","58.46",true,{"key":20,"text":21,"correct":14},"C","88.13",{"key":23,"text":24,"correct":14},"D","116.93","2020版教材P36 本题考查的是建设期利息的计算。各年应计利息=（年初借款本息累计+本年借款额／2）×年利率。本题的计算如下：第一年应计利息=1\u002F2×480×6%=14.4（万元）；第二年应计利息=（480+1\u002F2×480+14.4）×6%=44.06（万元）；建设期利息总和=14.4+44.06=58.46（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]