[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110013":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1110013,783,1,"单选题","国际工程项目建筑安装工程费用构成中，分包费的数额等于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分包商的报价",false,{"key":16,"text":17,"correct":14},"B","承包商对分包商的管理费",{"key":19,"text":20,"correct":14},"C","业主对分包商的管理费",{"key":22,"text":23,"correct":24},"D","分包商报价及相应总包管理费",true,"2020版教材P27 本题考查的是国际工程项目建筑安装工程费用构成的相关内容。这其中分包费指分包商的报价加总包管理费。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]