[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1110007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1110007,783,1,"单选题","关于联合试运转费的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试运转收入大于试运转支出的工程，不列此项费用",true,{"key":16,"text":17,"correct":18},"B","联合试运转费应包括单台设备调试费及无负荷联动试运转费用",false,{"key":20,"text":21,"correct":18},"C","试运转支出大于试运转收入的工程，不列此项费用",{"key":23,"text":24,"correct":18},"D","联合试运转支出主要是材料费，不包含人工费","联合试运转费是指新建企业或新增加生产工艺过程的扩建企业在竣工验收前，按照设计规定的工程质量标准，进行整个车间的负荷试运转发生的费用支出大于试运转收入的亏损部分。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]