[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109946,783,1,"单选题","已知某政府办公楼项目，税前造价为2000万元，其中包含增值税可抵扣进项税额150万元，若采用一般计税方法，则该项目建筑安装工程造价为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2180.0",false,{"key":16,"text":17,"correct":14},"B","166.5",{"key":19,"text":20,"correct":14},"C","2330.0",{"key":22,"text":23,"correct":24},"D","2016.5",true,"本题考查的是按费用构成要素划分的建筑安装工程费用项目组成和计算。建筑安装工程造价＝（2000-150）×（1+9%）=2016.5万元；销项税额＝（2000-150）×9%=166.5万元；应纳增值税额=166.5-150=16.5万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]