[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109938,783,1,"单选题","下列措施项目费中，（）可以予以计量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","夜间施工增加费",false,{"key":16,"text":17,"correct":14},"B","二次搬运费",{"key":19,"text":20,"correct":21},"C","脚手架工程费",true,{"key":23,"text":24,"correct":14},"D","安全文明施工费","2020版教材P19-23 措施项目费的计量分为国家计量规范规定应予计量的措施项目和国家计量规范规定不宜计量的措施项目。安全文明施工费、夜间施工增加费、二次搬运费、冬雨期施工增加费、已完工程及设备保护费均属于不宜计量的部分。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]