[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109916,783,1,"单选题","已知某世界银行项目各项数据如下：项目管理费600万元，开工试车费200万元，业主的行政性费用150万元，生产前费用500万元，运费和保险费100万元，地方税100万元，建设成本上升费120万元，则该项目间接建设成本为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","950",false,{"key":16,"text":17,"correct":14},"B","1450",{"key":19,"text":20,"correct":21},"C","1650",true,{"key":23,"text":24,"correct":14},"D","1770","2020版教材P11-13 项目间接建设成本包括项目管理费、开工试车费、业主的行政性费用、生产前费用、运费和保险费、地方税6项，则该项目间接建设成本=600+200+150+500+100+100=1650(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]