[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109910,783,1,"单选题","某建设项目投资构成中，设备及工器具购置费为1000万元，建筑安装工程费为2000万元，工程建设其他费为500万元，预备费为300万元，建设期贷款为1500万元，应计利息为80万元，流动资金贷款为300万元，则该建设项目的工程造价为（）万元",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3880",true,{"key":16,"text":17,"correct":18},"B","4180",false,{"key":20,"text":21,"correct":18},"C","5380",{"key":23,"text":24,"correct":18},"D","5680","2020版教材P11 该建设项目的工程造价=1000+2000+500+300+80=3880(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]