[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109909":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109909,783,1,"单选题","（2020年真题）下列费用中，属于静态投资的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设期利息",false,{"key":16,"text":17,"correct":18},"B","工程建设其他费",true,{"key":20,"text":21,"correct":14},"C","涨价预备费",{"key":23,"text":24,"correct":14},"D","汇率变动增加的费用","P1-2 本题考查的建设工程项目投资的概念。固定资产投资可分为静态投资部分和动态投资部分。静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的固定资产投资增加额，包括涨价预备费和建设期利息。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]