[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109905":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109905,783,1,"单选题","（2014年真题）下列项目监理机构施工阶段投资控制的措施中，属于技术措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审核承包人编制的施工组织设计",true,{"key":16,"text":17,"correct":18},"B","复核工程付款账单，签发付款证书",false,{"key":20,"text":21,"correct":18},"C","审核竣工结算",{"key":23,"text":24,"correct":18},"D","编制施工阶段投资控制工作计划","本题考查的是投资控制的措施。技术措施：（1）对设计变更进行技术经济比较，严格控制设计变更。（2）继续寻找通过设计挖潜节约投资的可能性。（3）审核承包人编制的施工组织设计，对主要施工方案进行技术经济分析。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]