[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109898,783,1,"单选题","为了有效地进行投资控制，下列选项中，可采取的技术措施是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取节约投资的奖励",false,{"key":16,"text":17,"correct":18},"B","深入技术领域研究节约投资的可能性",true,{"key":20,"text":21,"correct":14},"C","动态地比较项目投资的实际值和计划值",{"key":23,"text":24,"correct":14},"D","明确管理职能分工","2020版教材P5-6 为了有效地控制建设工程投资，应从组织、技术、经济、合同与信息管理等多方面采取措施。从组织上采取措施，包括明确项目组织结构，明确投资控制者及其任务，以使资控制有专人负责，明确管理职能分工；从技术上采取措施，包括重视设计多方案选择，严格审查监督初步设计、技术设计、施工图设计、施工组织设计，深入技术领域研究节约投资的可能性；从经济上采取措施，包括动态地比较投资的实际值和计划值，严格审核各项费用支出，采取节约投资的奖励措施等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]