[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109895,783,1,"单选题","工程项目建设过程中，（）是进行技术设计和施工图设计的投资控制目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计概算",true,{"key":16,"text":17,"correct":18},"B","施工图预算",false,{"key":20,"text":21,"correct":18},"C","修正概算",{"key":23,"text":24,"correct":18},"D","投资估算","2020版教材P4 设计概算应是进行技术设计和施工图设计的投资控制目标。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]