[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109891,783,1,"单选题","生产性建设工程总投资包括( )两部分。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设投资和建设期利息",false,{"key":16,"text":17,"correct":14},"B","静态投资、建设期利息和流动资金",{"key":19,"text":20,"correct":21},"C","建设投资、建设期利息和流动资金",true,{"key":23,"text":24,"correct":14},"D","固定资产投资和无形资产投资","2020版教材P1-2 建设工程项目投资是指进行某项工程建设花费的全部费用。生产性建设工程项目总投资包括建设投资和铺底流动资金两部分；非生产性建设工程项目总投资则只包括建设投资。 生产性建设工程项目总投资包括建设投资、建设期利息和流动资金三部分；非生产性建设工程项目总投资包括建设投资和建设期利息两部分。其中建设投资和建设期利息之和对应于固定资产投资。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]