[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109873,783,1,"单选题","建设项目静态投资考虑的因素是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","价格上涨风险引起的投资增加",false,{"key":16,"text":17,"correct":14},"B","因时间迁移而产生的单利利息支出",{"key":19,"text":20,"correct":14},"C","因时间迁移而产生的复利利息支出",{"key":22,"text":23,"correct":24},"D","因工程量误差而可能引起的投资增加",true,"2020版教材P1 本题考查的是建设投资中静态投资部分的概念。静态投资部分，是以某一基准年、月的建设要素的价格为依据所计算出来的建设项目投资的瞬间值。它还包含因工程量误差而引起的项目投资的增减。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]