[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109870,783,1,"单选题","建设工程投资控制的目的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资越少越好",false,{"key":16,"text":17,"correct":14},"B","中标价低于标底价",{"key":19,"text":20,"correct":21},"C","实现项目投资管理目标",true,{"key":23,"text":24,"correct":14},"D","控制动态投资","2020版教材P3 本题考查的是建设工程投资控制原理。所谓建设工程投资控制，就是在投资决策阶段、设计阶段、发包阶段、施工阶段以及竣工阶段，把建设工程投资控制在批准的投资限额以内，随时纠正发生的偏差，以保证项目投资管理目标的实现，以求在建设工程中能够合理使用人力、物力、财力，取得较好的投资效益和社会效益。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]