[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109866":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109866,783,1,"单选题","在建设单位和承包单位未能就工程变更的费用达成协议时，()应提出一个暂定的价格，作为临时支付工程款的依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","承包单位",{"key":19,"text":20,"correct":21},"C","项目监理机构",true,{"key":23,"text":24,"correct":14},"D","工程造价管理机构","⑷建设单位与施工单位未能就工程变更费用达成协议时，项目监理机构可提出一个暂定价格并经建设单位同意，作为临时支付工程款的依据。最终结算时，应以建设单位与施工单位达成的协议为依据。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]