[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109860,783,1,"单选题","下列施工阶段投资控制措施中，属于组织措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制资金使用计划",false,{"key":16,"text":17,"correct":18},"B","编制详细的工作流程图",true,{"key":20,"text":21,"correct":14},"C","对设计变更进行技术经济分析",{"key":23,"text":24,"correct":14},"D","对投资支出作出分析与预测","2020版教材P5-6 项目监理机构在施工阶段投资控制的组织措施： (1) 在项目监理机构中落实从投资控制角度进行施工跟踪的人员、任务分工和职能分工。 (2) 编制本阶段投资控制工作计划和详细的工作流程图。 选项A、D属于经济措施，选项C属于技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]