[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109853,783,1,"单选题","在建设项目投资各阶段中，下列影响项目投资的可能性最高的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步设计",true,{"key":16,"text":17,"correct":18},"B","技术设计",false,{"key":20,"text":21,"correct":18},"C","施工图设计",{"key":23,"text":24,"correct":18},"D","施工剩余设计","2020版教材P4-5 影响项目投资最大的阶段，是约占工程项目建设周期四分之一的技术设计结束前的工作阶段。在初步设计阶段，影响项目投资的可能性为75%~95%；在技术设计阶段，影响项目投资的可能性为35%~75%；在施工图设计阶段，影响项目投资的可能性则为5%~35% 。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]